MDOT SHA PLANNED MAJOR LANE CLOSURE UPDATE FOR WEEKEND OF SEPTEMBER 17, 2021

MDOT SHA Logo

MDOT SHA Logo

Real-Time travel conditions and live traffic cameras md511.maryland.gov

Weekend

Baltimore County     

  • I-695/I-70 Interchange – Routine Bridge Inspections Scheduled -
    • Saturday, September 18: 1 a.m.-6 a.m. Ramp Closure: Southbound I-695 (Outer Loop) to eastbound I-70.  Detour: Take southbound I-695 exit ramp to Edmondson Avenue and loop back to I-70. 
    • Sunday, September 19: 1 a.m.-6 a.m. Ramp Closure: Northbound I-695 (Inner Loop) to westbound I-70. Detour: Take eastbound I-70 to Park and Ride Lot, turn around to westbound I-70.    
  • US 40 Dual Bridges over Little Gunpowder Falls and (Big) Gunpowder Falls – Bridge Replacement - Single lane closures on US 40 East and West in the vicinity of the bridges at any time between 7 a.m. and 4 p.m. on Saturdays through fall 2021.          

Week Ahead

Allegany County  

  • I-68 (National Freeway) – Eastbound Exit 40 to US 220 South and Westbound Seton Drive Exit to the top of Haystack. Lane Closures -  8 p.m.-6 a.m. – patching. Sunday-Thursday.
  • US 220 – Barton Park Drive to Bell Street – Single Lane Closures – 10 p.m.-6 a.m. – Patch, mill and resurface.     
  • MD 639 (Willowbrook Rd) - Single Lane Closure - 8:00 p.m.-6:00 a.m. - Nighttime flagging operation in the lower roundabout. Patching. Sunday-Thursday  New

Anne Arundel County

  •  MD 214 between River Club Drive and Mayo Avenue – Nighttime flagging operation between 9 p.m. and 5 a.m., Sunday through Thursday nights (County public works project).   
  • MD 169 between Hammonds Ferry Road and MD 648 - Daytime flagging operation, 7 a.m. to 5 p.m., Monday through Friday.      
  • MD 176 between Wright Road and Arundel Mills Boulevard/New Ridge Road – Daytime single lane closures, 8 a.m. to 4 p.m., Monday through Friday.      
  • MD 450 between Annapolis Street to US 50 (John Hanson Highway) near the Naval Academy Bridge – overnight patching and resurfacing, Sunday through Thursday night, 9 p.m. to 5 a.m.       

Baltimore City          

  • HIGH IMPACT  I-895 (Baltimore Harbor Tunnel Throughway) between the tunnels and Boston Street/O’Donnell Street (exit 11) and the Holabird Avenue exit (MDTA Project) – Bridge rehabilitation project – Expect lane closures during off-peak travel times into summer 2021.                  

Baltimore County       

  • I-695 Outer Loop from MD 43 to I-83 North (BHX) – Concrete Median Barrier Inspection – Daytime left shoulder closures at various inspection areas between 9 a.m. and 3 p.m. Tuesday 9/21 through Friday 9/21.   
  • MD 122 (Security Blvd.) from Rolling Rd to East of I-695 - Highway Maintenance roadway milling, patching and resurfacing - Weeknight single lane closures between 9 p.m. and 5 a.m. the next day, Sunday-Thursday through mid-October 2021.   
  • MD 137 (Mt. Carmel Rd.) from Gunpowder Rd. to MD 25 (Falls Rd.) - Highway Maintenance roadway pavement milling, patching and resurfacing - Weekday single lane closures with flagging operations on MD 137 between 9 a.m. and 3 p.m. Monday - Friday, in summer 2021.       
  • MD 45 (York Rd.) from Gifford Rd. to Middletown Rd. - Highway Maintenance roadway pavement milling, patching and resurfacing – Single lane closures with flagging operations on MD 45 between 9 a.m. and 3 p.m. Monday-Friday, in summer 2021.                           

Carroll County 

  • MD 26 (Liberty Road) between Calvert Way and Monroe Avenue - Highway maintenance roadway patching and resurface – Single lane closures overnight from 8 p.m. to 5 a.m. Sunday nights through Friday mornings. The project is expected to be complete in October.

Frederick County

  • I-270: Exit ramp from southbound I-270 to northbound MD 85 and exit ramp from northbound MD 85 to southbound I-270 - Pipe installation - Overnight closures from 9 p.m. to 5 a.m. Sunday night through Friday. The work and closures are expected to continue through the summer season.      
  • MD 80 (Fingerboard Road) between Thurston Road and MD 355 (Urbana Pike) - Highway maintenance pavement patching - Single lane closures and flagging Sundays through Thursdays from 8 p.m. until 5 a.m. the next morning. MD 80 ramps at northbound I-270 will close when crews work at that location. Motorists will be detoured. This project is expected to be complete in October.       
  • MD 26 (Liberty Road) between MD 194 and Chestnut Grove Road– Highway maintenance pavement patching and overlay – Single lane closures Monday through Friday from 8 a.m. to 4 p.m. starting Monday, September 20. Saturday daytime work is possible. The project is expected to be complete in November. New
  • MD 17 (Burkittsville Road) between US 340 and the border of Burkittsville, north of Brownsville Pass Road – Highway maintenance pavement patching and overlay – Single lane closures Monday through Friday from 8 a.m. to 5 p.m. Saturday daytime work is possible. The project is expected to be complete in November.
  • US 40 Alternate between Mount Tabor Road and west of Dahlgren Road – Highway maintenance crack sealing - Mobile work crew crack sealing on the roadway surface with a flagging operation from 8 a.m. to 4 p.m. starting Monday, September 20. The project is expected to take about four days to complete. New

Garrett County   

  • US 40 Alt – Pennsylvania State Line to US 219 South – Single Lane Closures – 6:30 a.m.-7:00 p.m. – Patch, mill and resurface.   
  • US 219 from the Intersection of Green St / Third St to the Intersection of Oak Street /MD 135 - single lane closures – flagging operation – 8:00 p.m.-5:00 a.m. - crack sealing. 

Harford County 

  • US 40 (Pulaski Hwy.) from Robinhood Rd. to MD 7A (Post Rd./Revolution St.) –  Highway maintenance pavement repair, milling and resurfacing in Havre de Grace - Overnight single lane  closures and lane shifts on eastbound and westbound US 40  Sunday-Thursday, between 7 p.m. and 5 a.m. the next day, through late September 2021.     
  • US 40 (Pulaski Hwy.) MD 7A (Post Rd./Revolution St.) to Otsego St. – Highway maintenance pavement repair, milling and resurfacing in Havre de Grace - Daytime single lane  closures and lane shifts on eastbound and westbound US 40  Monday-Friday between 9 a.m. and 3 p.m. through late October 2021.    
  • MD 624 (Graceton Rd.) from MD 165 (Pylesville Rd.) to MD/PA State line – Highway Maintenance paving work -  Weekday single lane closures with flagging operations between 9 a.m. and 3 p.m. Monday-Friday, Saturdays when needed between 6 a.m. and 2 p.m. through mid-October 2021.    
  • MD 24 (Vietnam Veterans Memorial Hwy.) - Pavement resurfacing project - Overnight single  lane closures and traffic shifts Sunday through Thursday 8 p.m.-5 a.m. the next day  through late September 2021.                              

Howard County         

  • MD 32 (Patuxent Freeway) between the Anne Arundel County line, south of Dorsey Run Road, and US 1 – Highway maintenance patching and resurfacing – Single lane closures with a flagging operation overnight Sundays through Thursdays until 5 a.m. the following day. The project is expected to be complete in November. New
  • MD 32 (Patuxent Freeway) between Fox Chase Road and the Burntwoods Road interchange – Traffic lane switch – On Sunday, September 19 at 9 p.m., crews will have single lane closures and a flagging operation to move traffic in both directions from the existing travel lanes to the newly constructed roadway. The exit ramp on southbound MD 32 to Ten Oaks Road will also be closed overnight. Motorists will be detoured to Linden Church Road and take northbound MD 32 to access the Burntwoods Road interchange and Ten Oaks Road. The work will end by 5 a.m. the following day on Monday, September 20. Updated
  • MD 108 (Clarksville Pike) between Linden Linthicum Lane and the Little Patuxent River bridge, east of Davidge Drive – Highway maintenance patching and resurfacing - Single lane closures with a flagging operation Sundays through Thursdays from 9 p.m. to 5 a.m. the following morning. The project is expected to complete in November. New
  • MD 32 (Patuxent Freeway) at Dorsey Run Road – Road surface improvement project – Single lane closures on MD 32 and Dorsey Run Road between 7 p.m. and 6 a.m. along with daytime single lane closures Dorsey Run Road. All interchange ramps are currently open. Ramp C (Westbound MD 32 to Dorsey Run Road) is expected to close for work on one weekend later this month. Updated

Montgomery & Prince George’s  Counties

  • Purple Line – For a list of active construction and lane closures along the Purple Line alignment, please click HERE (MTA project).     

Montgomery County  

  • MD 410 (East West Highway) at MD 186 (Brookville Road). Inlet/sidewalk construction project. Single, off-peak lane closures, weekdays, 9 a.m. to 3 p.m. through year-end 2021.
  • MD 650 (New Hampshire Avenue) from the I-495 (Capital Beltway) ramps to Oakview Drive. Resurfacing project. Single and multiple off-peak lane closures, weekdays 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 9 p.m. to   5 a.m. through late fall 2021.  

Prince George’s County   

  • Inner Loop/Outer Loop of I-95/I-495 (Capital Beltway) from MD 5 (Branch Avenue) Hill Road to MD 414 (St. Barnabas Road). Roadway patching. Single and multiple off-peak lane closures, overnight, Sunday through Friday, 7 p.m. to 5 a.m. through late fall 2021.    
  • MD 223 (Woodyard Road) from Sherwood Drive to Victoria Drive. Sidewalk  construction project. Off-peak lane closures, weekdays, 8:30 a.m. to 3:30 p.m. and  Saturdays, 8 a.m. to  5 p.m. through late fall 2022.     
  • MD 223 (Woodyard Road) at Dower House Road. Geometric improvement p project. Single weekday lane closures, 9 a.m. to 3 p.m. and overnight, Sunday through  Thursday, 9 p.m. to 5 a.m. through year-end 2021.    
  • I-95/I-495 (Capital Beltway) from Suitland Road to MD 4 (Pennsylvania Avenue).  Suitland Parkway bridge replacement project. Off-peak single and multiple lane  closures, weekdays, 9 a.m to 3 p.m. and overnight, Sunday through Friday, 9 p.m. to  5 a.m. through year-end  2021. 

St. Mary's County

  • MD 5 between Abell/Moakley Streets and MD 245 (Hollywood Road) - Overnight single lane closures between 9 p.m. and 5 a.m., Sunday through Thursday nights.    
  • MD 5 between Camp Brown Road and Scotland Beach Road – daytime single lane closures between 8 a.m. and 4 p.m.

Washington County 

  • MD 63 – Transportation Circle to Williamsport – Lane Shift – 7 a.m.-6 p.m. Weekdays – Patch, grind and resurface. New   
         

Worcester County 

  • MD 367 (Bishopville Road) from US 113 to Delaware line – Single lane closures 8 p.m.-6 a.m. weekdays through 9/30. Patch, mill and resurface. Commercial vehicle operators should use alternate routes during work hours due to soft shoulders - New  

Long-Term Closures

Allegany County     

  • MD 51 (Industrial Boulevard) between Canal Parkway and Second Street – Bridge Rehabilitation – Northbound side of bridge closed - traffic is shifted onto the southbound side of the bridge – one lane traffic in each direction.   
  • MD 51 (Oldtown Road) over the C&O Canal near Paw Paw Tunnel – Bridge Rehabilitation - both lanes are closed and a temporary traffic signal is rotating traffic through a single center lane.   
  • MD 135 West of the MD 36 Intersection and MD 135 and River Road area Westernport/Bloomington – Bank stabilization - northbound lane will be closed – southbound lane will be used for commute lane. Traffic signage, barriers, lights and flaggers will be in place for directing and maintaining traffic control.
      

Anne Arundel County

  • MD 2 between Pasadena Road and MD 270 (Furnace Branch Road) - Overnight single lane  closures, Sunday through Thursday nights, 9 p.m. and 5 a.m.          
  • MD 32 at MD 3 interchange – Ramp resurfacing, Sunday through Thursday nights 9 p.m. and 5 a.m.                     

Baltimore County                 

  • Cove Road bridge over I-695 - Bridge deck replacement - On I-695, daytime single lane closures in both directions may occur Monday-Friday between 9 a.m. and 3 p.m. and overnight  lane closures Sunday-Thursday between 7 p.m. and 5 a.m. the next day. On Cove Road  bridge over I-695, long-term single lane closures are in effect, with two-way traffic on the southern side of the bridge deck as of August 16.   
  • I-70 bridges over Patapsco River and CSX Rail Line at Baltimore/Howard Co. Line –  Bridge Parapet Rehabilitation - Single lane closures Monday-Friday between 9 a.m. and  3 p.m. and overnight single and double lane closures Sunday-Thursday between 7 p.m.  and 5 a.m. the next morning. Lane closures permitted when needed on Saturdays  between 9 a.m. and 3 p.m.                  
  • I-83 (Baltimore-Harrisburg Expressway) North and South Bridges over Padonia Road – Dual Bridge replacement and interchange improvements. There may be single lane  closures on I-83 North and I-83 South between 9 a.m. and 4 p.m. Monday-Friday and  between 7 p.m. and 5 a.m. the next day Sunday-Thursday. Single lane closures on  Padonia Rd. West between 9 a.m. and 3 p.m. Monday-Saturday, and between 8 p.m.  and 5 a.m. the next day Sunday-Thursday.  Detours of Padonia Rd. underneath I-83  possible on any weeknights (Sunday-Thursday) between 8 p.m. and 5 a.m. the next  morning. Note: Interchange Ramp from Padonia Road East to I-83 North closed 24  hours/7 days until project is complete.                     
  • MD 695A (Broening Hwy.) between Maryland Ave. and east of Ralls Ave. at Baltimore  City/County Line in Dundalk - Roadway Resurfacing and Safety Improvements –  Daytime single lane closures on Broening Hwy. between 9 a.m. and 3 p.m. Monday-Thursday and between 9 a.m. and 2 p.m. Friday. Overnight double lane closures with  traffic lane shifts on Broening Hwy. between 8 p.m. and 5 a.m. the next day Sunday-Thursday.      
  • US 40 Dual Bridges over Little Gunpowder Falls and (Big) Gunpowder Falls – Bridge  replacement – Weekdays: Single lane closures Eastbound US 40 (towards Aberdeen) 6 a.m. to 4 p.m.  Westbound US 40 (towards Baltimore) 8 a.m. to 4 p.m.  Weeknights: Single lane closures Eastbound and  Westbound US 40  8 p.m. to 5 a.m. the next day, Sunday-Thursday nights. Saturdays: Single lane closures Eastbound and Westbound US 40 in the vicinity of the bridges at any  time between 7 a.m. and 4 p.m. on Saturdays.     
  • US 1 (Washington Blvd.) Bridge over CSX Transportation rail lines – Bridge replacement  – As of June 10, Clarke Blvd. at US 1 is closed/detoured 24 hours, 7 days/week for  one year.  Posted detour route includes Selford Rd., Francis Ave., Oregon and  Carville Aves., Tom Day Blvd. and US 1 Alt. (Southwestern Blvd.).               
  • MD 43 (White Marsh Blvd.) at Honeygo Blvd. - Intersection Widening and  Improvements - Temporary daytime lane closures on MD 43 and Honeygo Blvd. legs of the intersection between 9 a.m. and 3 p.m. Monday-Friday, and overnight lane  closures at any time between 8 p.m. and 5 a.m. the next day Sunday-Thursday. When  necessary, there will be temporary lane closures on weekends, 7 a.m.-1 p.m.                 
  • MD 45 (York Road) between north of Padonia Road and Wight Avenue – Roadway resurfacing/county water main replacement – Single and double lane closures on MD  45 for overnight final paving and marking work between 9 p.m. and 5 a.m. the next day  Sunday-Thursday and single lane closures where needed between 9 a.m. and 3 p.m.  Monday-Friday through September.                        
  • MD 140 (Reisterstown Rd.) between Painters Mill Rd. and E. Pleasant Hill Rd. – Resurfacing/County Water Main replacement - Crews currently installing new 36-inch  water main from Owings Mills Blvd. to East Pleasant Hill road with connections to fire  hydrants and buildings along MD 140. Daytime single lane closures  between 9 a.m. and  3 p.m. between Owings Mills Blvd. and E. Pleasant Hill Rd.  Night time single lane  closures within project limits Sunday-Thursday nights between 9 p.m. and 5 a.m. the  next day.  Access to all driveways in this section will be maintained during any lane closures.      
  • MD 140 (Reisterstown Rd.) between E. Pleasant Hill Rd. and Stocksdale Ave. – Resurfacing/County Water Main replacement - Daytime single lane closures Monday-Friday 9 a.m.-3 p.m. between E. Pleasant Hill Rd and Stocksdale Ave.  Night time single lane closures within project limits Sunday-Thursday nights between 8 p.m. and 6 a.m. the next day.  Access to driveways in this section will be maintained during any lane  closures.                 
  • MD 147 (Harford Rd.) / Joppa Rd. - Intersection Improvements - Daytime single lane  closures and flagging operations on Harford and Joppa Road in the vicinity of the  intersection Monday-Thursday 9 a.m.-4 p.m. Monday-Thursday and 9 a.m.-3 p.m. Fridays. Overnight work with lane closures Sunday-Thursday 9 p.m.-5 a.m. the next  day. Traffic lane shift now in effect 24/7 along southbound MD 147 at Joppa Rd.                   
  • MD 151 (Sparrows Pt. Blvd.) / Wharf Road (MD 151 B) Interchange - Three-bridge  replacement project at interchange.  The southbound side of the existing MD 151 bridge  is closed and two-way traffic - one lane in each direction - runs on the northbound side  of the bridge. This will be in effect for the next year and will enable partial demolition of  the existing bridge over Wharf Road and future construction of the new bridge. This is in addition to the detours of southbound and northbound Wharf Road at the interchange.  
    • NOTES: As of May 12, 2021 the northbound side of MD 151 is closed between the Baltimore County Highways Maintenance Shop (1500 block) and the Wharf Rd. Interchange.  Two-way traffic will run on the southbound side of MD 151 , one lane in each direction. The  existing ramp from Northbound MD 151 to southbound Wharf Road is open for local  traffic only.

Cecil County

  • MD 279 (Elkton Road) at MD 277 (Fletchwood Road) – Northbound MD 279 is reduced to a single lane at the MD 277 intersection near the Delaware line and shifted across the median to a contraflow pattern (one lane in each direction) through summer 2021. This is part of the Delaware Department of Transportation (DelDot) reconstruction of route 279.  Updated                   

Frederick County                      

  • I-270 (Eisenhower Highway) southbound from MD 121 (Clarksburg Road) to MD 109 (Old Hundred Road) I-270 acceleration lane expansion project. Single and multiple off-peak lane closures, weekdays 9:30 a.m.to 3:30 p.m. and overnight, Sunday through Thursday, 7 p.m. to 4 a.m. through year-end 2021.  Possible Traffic Impact in Frederick County.

Harford County

  • Old Joppa Road Bridge over I-95 (MDTA project) – Bridge replacement project – Old Joppa Road closed and locally detoured.                                
  • Clayton Road bridge over I-95 between MD 152 and MD 24 (MDTA project) - Clayton Road closed and detoured until early 2022.                               
  • MD 22 (Churchville Road) between MD 136 (Calvary Road) and Prospect Mill Road -Roadway resurfacing and intersection widening – Occasional single lane closures/lane shifts on MD 22 east and west of Thomas Run Road/Shucks Road intersection when necessary between 9 a.m. and 3 p.m. Monday-Friday, and between 8 p.m. and 5 a.m. the next day Sunday-Thursday and between 7 a.m. and 1 p.m. Saturdays when necessary through late summer 2021.     
  • MD 924 South (Kenmore Avenue) between US 1 and Main Street, and MD 924 (Emmorton Road) between Ring Factory Road and Plumtree Road -Roadway resurfacing and traffic signal upgrades - Occasional concrete curb, ramp, sidewalk work on sections of MD 924 through spring 2021.  MD 924 from Ring Factory Rd. to Plumtree Rd. Monday-Friday, 9 a.m.-3 p.m. and Sunday-Thursday, 9 p.m. until 5 a.m. the next day; MD 924 from US 1 to Kenmore Ave. Monday-Friday, 9 a.m.-3 p.m. and Sunday-Thursday, 9 p.m.-5 a.m. the next day through late summer 2021.                

Montgomery County    

  • MD 410 (East West Highway) at MD 186 (Brookville Road). Inlet/sidewalk construction project. Single, off-peak lane closures, weekdays, 9 a.m. to 3 p.m. through year-end 2021.   
  • MD 185 (Connecticut Avenue) at Jones Bridge Road/Kensington Parkway. Intersection improvement project. Single off-peak lane closures on MD 185, weekdays, 9 a.m. to  3 p.m. and overnight, Sunday through Thursday, 9 p.m. to 5 a.m. and single off-peak lane closures on Jones Bridge Road, weekdays, 9 a.m. to 3 p.m. and overnight, 7 days per week, 9 p.m. to 5 a.m. through late summer 2023.     
  • US 29 (Colesville Road) from St. Andrews Way to Stewart Lane. -Safety and resurfacing project - Single daytime lane closures, weekdays, 9 a.m. to 3 p.m. and single/multiple off-peak overnight lane closures, Sunday through Thursday, 7 p.m. to  5 a.m. through year-end 2021.   
  • MD 97 (Georgia Avenue) from north of Gold Mine Road to south of Holiday Drive. - Roadway relocation project.- Intermittent single northbound and southbound lane closures weekdays, 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 9 p.m. to 6 a.m. through year-end 2022. 
  • MD 190 (River Road) from MD 188 (Wilson Lane) to MD 614 (Goldsboro Road). Roadway improvement project. Single lane closures, weekdays, 9 a.m. to 3 p.m. and multiple lane closures, overnight, 9 p.m. to 5 a.m. through late fall 2021.  
  • MD 185 (Connecticut Avenue) from MD 547 (Knowles Avenue) to Dupont Avenue. Geometric/median improvement project. Single and multiple off-peak northbound and southbound lane closures, weekdays, 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 9 p.m. to 6 a.m. through year-end 2021.
  • I-270 (Eisenhower Highway) from Interstate 70 to I-495 (Capital Beltway). Traffic congestion relief construction project - Intermittent single lane closures, weekdays, 10 a.m. to 3 p.m. and single, double and triple overnight lane closures, Sunday through Thursday, 7 p.m. to 5 a.m. and intermittent temporary ramp closures with detours up to 24 hours a day through year-end 2021. 
  • I-270 (Eisenhower Highway) southbound from MD 121 (Clarksburg Road) to MD 109 (Old Hundred Road). I-270 acceleration lane expansion project. Single and multiple off-peak lane closures, weekdays 9:30 a.m.to 3;30 p.m. and overnight, Sunday through Thursday, 7 p.m. to 4 a.m. through year-end 2021.
  • Seminary Road from Hale Street to MD 192 (Forest Glen Road) - Bridge rehabilitation project - Intermittent left and right single northbound and southbound lane closures, weekdays, 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 8 p.m. to 5 a.m. through late fall 2021.
  • Inner and Outer Loop of I-495 (Capital Beltway) from MD 97 (Georgia Avenue) to MD 185 (Connecticut Avenue). Bridge rehabilitation project. Intermittent single weekday single lane closures, 9 a.m. to 3 p.m. and intermittent off-peak single and multiple  lane closures with intermittent  full traffic stops, Sunday through Thursday, 9 p.m. to 5 a.m. through late fall 2021. 

Prince George’s County             

  • US 1 (Baltimore Avenue) College Ave. to MD 193 (University Boulevard) - US 1 Reconstruction Project - Corridor Improvement- Northbound and southbound single lane closures throughout the length of the project Saturday through Sunday, 10 a.m. to 4 p.m. and 9 p.m. to 7 a.m. through late summer 2023.   
  • MD 5 (Branch Avenue) from the DC Line to the intersection of Curtis Drive. Safety and resurfacing project. Intermittent/temporary single and multiple MD 5 northbound off-peak lane closures, weekdays, 9 a.m. to 3 p.m., overnight, Sunday through Thursday 7 p.m. to 5 a.m. and weekends, 5 a.m. to 10 p.m. and weekends 5 a.m. to 10 p.m. Intermittent/temporary single and multiple MD 5 southbound off-peak lane closures weekdays, 6 a.m. to 12 noon overnight, Sunday through Thursday, 7 p.m. to 6 a.m. and intermittent/temporary single and multiple MD 637 single lane closures, weekdays, 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 7 p.m. to 6 a.m. through late spring 2022.
  • MD 210 (Indian Head Highway) at Kerby Hill Road/Livingston Road. Interchange construction project. Intermittent single and multiple-off peak lane closures on all roads, weekdays, 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 9 p.m. to 5 a.m. through year-end 2021.   
     MD 212A (Powder Mill Road) from Pine Street to US 1 (Baltimore Avenue). Roadway reconstruction project. Intermittent single and multiple lane closures weekdays, 8 a.m. to 4 p.m. through late summer 2022.    
  • Eastbound MD 214 (Central Avenue) ramp to northbound I-95/I-495 (Capital Beltway). Bridge construction project. Full ramp closure with detour through year-end 2021. Drivers should use the signed detour route of eastbound MD 214 to northbound MD 202 (Largo Road) to westbound MD 214 to access northbound I-95/I-495).      
  • MD 500 (Queens Chapel Road) from Eastern Avenue to MD 208 (Hamilton Street). Community safety and enhancement project. Intermittent single and multiple lane closures weekdays, 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 7 p.m. to 6 a.m. through late summer 2022.  
    Southbound I-95/I-495 (Capital Beltway) ramp to eastbound MD 214 (Central Avenue) – Bridge replacement project – Total ramp closure with traffic using the Capital Beltway/MD 202 (Largo Road) interchange and then to MD 214 via MD 202 to year-end 2021.        
  • I-95/I-495 (Capital Beltway) over Suitland Road. Bridge replacement project. Intermittent single and multiple lane closures, weekdays, 7 a.m. to 5 p.m. and overnight, Sunday through Thursday, 8 p.m. to 5 a.m. and weekends, Saturday night 6 p.m. to 11 a.m. Sunday morning through late fall 2021.
  • I-95/I-495 (Capital Beltway) from Suitland Road to MD 4 (Pennsylvania Avenue). Suitland Parkway bridge replacement project. Road shoulder closure permissible 24 hours daily, intermittent single and multiple lane closures, weekdays, 9 a.m. to 3 p.m. and overnight, Sunday through Friday, 8 p.m. to 6 a.m. through year-end 2021. 

Washington County             

  • I-70 Eastbound and Westbound at the MD 65 Interchange – Bridge rehabilitation and widening of I 70 bridge over MD 65- Left shoulder closed EB/WB long term for phase 1 work. Intermittent, single lane closures at nighttime from Sunday through Thursday between midnight and 5 a.m. on I-70. Additionally, alternating/single lane closures will be performed between 9 a.m. and 3 p.m., weekdays on MD 65 North and South.  

 

###