SHA PLANNED LANE CLOSURE UPDATE (02/17/2017 – 02/21/2017)

MDOT SHA Logo

MDOT SHA Logo

(All Work is Weather Permitting and is subject to change.  List will be updated by 3 p.m. Friday.)
 
Major Weekend Lane Closures

Anne Arundel County

• Inner loop of I-695 (Baltimore Beltway) ramp to southbound MD 10 (Arundel Expressway) – Concrete patching – Ramp closure and local detour beginning 6 a.m. Saturday until 5 a.m. Monday.
 
Baltimore County

• Outer loop of I-695 (Baltimore Beltway) at MD 147 (Harford Road) Bridge work and overhead sign installation as part of interchange reconstruction – Two right lanes to be closed on the outer loop Sunday through Thursday between 9 p.m. and 5 a.m.  The on and off ramps the outer loop of I-695 at southbound Harford Road will also be closed.
 
• MD 139 (Charles Street) under the Joppa Road overpass – Routine bridge repairs – Single lane closure Saturday between 6 a.m. and 3 p.m.

• MD 7 (Philadelphia Road) between MD 588 (Golden Ring Road) and Rossville BoulevardRestriping pavement as last part of resurfacing project – Single lane closures beginning at 10 p.m. Sunday until 5 a.m. Monday.

Howard County

• Northbound I-95 between MD 216 (Scaggsville Road) and MD 32 Bridge cleaning and painting – Single lane closure at 9 p.m. Sunday until 5 a.m. Monday.

Montgomery County

 Northbound MD 97 (Georgia Avenue) between Spring Street and Cameron Street - Commercial building repairs - Single lane closures with partial sidewalk closures Saturday and Sunday between 9 a.m. and 6 p.m.

Total Closures with Detours

Baltimore County

• MD 147 (Harford Road) at Glen Arm Road/Mt. Vista RoadRoundabout construction – Mt. Vista Road leg of intersection is closed and detoured.  The detour is Sunshine Avenue to US 1 (Belair Road.) 

Dorchester County

• Woods Road closed north of MD 16 (Church Creek Road)Roundabout construction – The detour is US 50 to MD 16. 

Montgomery County

• MD 195 (Carroll Avenue) between Jefferson Avenue and Flower Avenue (MD 195 Bridge over Sligo Creek and Parkway) - Bridge rehabilitation – Bridge to closed and traffic detoured for one year. 

Wicomico County

• MD 349 (Nanticoke Road) Bridge over Windsor Creek - Bridge replacement – Bridge closed and detoured. Bridge deck (driving surface) is poured.
 
A look ahead at next week (High Impact)

Anne Arundel County

 I-895 (Harbor Tunnel Thruway) Bridge over the Patapsco River (Patapsco Flats) (MDTA project)Bridge rehabilitation – Reduced lanes. 
 
Howard County

• Ramp from eastbound Broken Land Parkway to northbound US 29 Highway widening project - Full ramp closure with posted detour beginning at 8 p.m. Monday until 5 a.m. Tuesday.
 
Montgomery County

• Inner loop I-495 (Capital Beltway) at exit #30/US 29 (Colesville Road) Steel repairs on bridge – Double right lane closures, as well as temporary ramp closure to US 29 on February 21 and 22 between 9 p.m. and 5 a.m. each subsequent morning.

• Inner loop of I-495 (Capital Beltway) ramp to MD 187 (Old Georgetown Road)Ramp drainage work – Ramp closure and detours scheduled for Tuesday, 2/21 between 10:00 p.m. and 2:00 a.m. 

• Ramp from southbound MD 185 (Connecticut Avenue) to the inner loop of I-495 (Capital Beltway) - Ramp drainage work - Full ramp closure with posted detour Thursday between 2 a.m. and 5 a.m.

Talbot County

• US 50 (Ocean Gateway) between east of Backtown Road and Timberwind Lane Emergency pipe repair – Traffic switch to a bidirectional traffic pattern until late-March.  Click here for more information and a diagram of the proposed traffic configuration.

Washington County
 
• I-81 between the bridge over the Potomac River and MD 63/MD 68 (Lappans Road)Highway widening and bridge rehabilitation project – Single left lane closures between 9 p.m. and 5 a.m. Sundays through Fridays.
 
Wicomico County

• Southbound US 13 ramp to southbound 13/eastbound US 50 (Salisbury Bypass) - Bridge rehabilitation project– Traffic pattern change/bidirectional traffic using median for bridge deck project.
 