The State Highway Administration (SHA) will patch and repair MD 151 (North Point Blvd./Sparrows Point Blvd.) between MD 695 (Baltimore Beltway/Patapsco Freeway) and Seventh Street beginning Tuesday, December 11.
Crews will temporarily close lanes and have flagging operations along sections of MD 151 between 9 a.m. and 3 p.m. Monday through Friday. SHA will work on weekdays as weather permits during the winter; however, crews may work between 6 a.m. and 2 p.m. on Saturdays if necessary. There will be no temporary lane closures on the Christmas and New Year’s holidays.
SHA’s contractor for the $460,000 project is American Infrastructure, Inc. of Fallston. Weather permitting, the pavement repair and patching project will be complete late February 2013.
Citizens with questions about this project may contact Mr. Michael Boardwine or Mr. Mike Wetzel, District Operations Engineers in SHA’s District 4 Office - Maintenance Division. They may be reached at 410-229-2360, toll-free at 1-866-998-0367 or by email at