SHA PLANNED LANE CLOSURE UPDATE (12/06 TO 12/13)

MDOT SHA Logo

MDOT SHA Logo


Baltimore County
• Northbound I-795 between I-695 and Owings Mills - Concrete patching. Weeknights: Sunday – Thursday from 7 p.m. – 5 a.m. the next morning.  If needed, double lane closures after 10 p.m.
 
 
Montgomery County
• Southbound MD 185 (Connecticut Avenue) between Saul Road and Washington Street – Retaining wall construction. Single lane closures on southbound MD 185 on Saturday, December 8 at 8 a.m. until 4 p.m.

 
Prince George’s County
• Southbound I-95/I-495 (outer loop of the Capital Beltway) at MD 201 (Kenilworth Avenue) – Bridge replacement project. Beginning 9 p.m. Friday, December 7, crews will begin lane closures to remove the demolition shield of the MD 201 Bridge over I-95 in Greenbelt.  Three right lanes will be closed beginning at 12 midnight.  All lanes will be open by 8 a.m. Saturday, December 8. 
 
• Westbound MD 193 (Greenbelt Road) between Cherrywood Lane and Branchville Road - Concrete bus pad construction. SHA will close the two right lanes on eastbound MD 193 beginning at 8 p.m. this Friday, December 7. All lanes will be open to traffic no later than 12 noon on Sunday, December 9.
 
 
Queen Anne’s County
• Westbound US 50 over US 301 – Bridge rehabilitation. project-left lane closed on westbound US 50. 
###​

###