PLANNED MAJOR LANE CLOSURE UPDATE FOR THE WEEKEND OF JANUARY 20, 2023        

MDOT SHA Logo

MDOT SHA Logo

​All work is weather dependent            

Real-time travel conditions and live traffic cameras – https://md511.maryland.gov

Week Ahead

Anne Arundel County  
MD 170 between Mathison Way and MD 176 – Northbound MD 170 shoulder and single lane closure for pipe replacement project, 9 a.m. to 3 p.m. weekdays through February 2023.   


MD 173 bridge over Stoney Creek - On Friday, January 27 from 6 a.m. to 2:30 p.m., crews will be performing routine maintenance that may consist of test openings. New
  
Baltimore County                   
I-95 at I-695 Southwest Interchange - Bridge Rehabilitation - Traffic shifts, shoulder and lane closures and interchange ramp detours for multi-bridge rehabilitation project. All dates/times weather permitting and subject to change.      


Sunday, January 22 - 26   
Ramp closures: 
Ramp from I-95 southbound to I-695 eastbound Outer Loop - Overnight closure, 8 p.m.to 5 a.m. 
Ramp from I-695 eastbound Outer Loop to I-95 northbound - Overnight closure, 8 p.m.to 5 a.m.  
Lane closures: 
I-695 Inner Loop and Outer Loop – Overnight single lane closures, 8 p.m. to 5 a.m. 
I-695 Inner Loop – Overnight double lane closures, 10 p.m. to 5 a.m. 


I-695 TSMO Project I-70 to MD 43
Week of Sunday, January 22 – Friday, Jan. 27  
Lane closures:
I-695 West/South (Outer Loop) from MD 139 (Charles St.) to I-70 – ITS underground installation and roadway construction –Daytime right shoulder closures between 9 a.m. and 3 p.m. Monday, Jan. 23 through Friday, Jan. 27.
I-695 East and West (Inner and Outer Loops) from MD 45 (York Rd.) to US 1 (Belair Rd.)  – Design Build Team field review – Overnight intermittent single lane/shoulder closures between 8 p.m. and 5 a.m. the next day , Sunday Jan. 22 through Thursday, Jan. 26.
 
I-695 Bridges over Morse Lane and Norfolk Southern RR – Cleaning & Painting of Bridges - Daytime single lane closures on I-695 Inner and Outer Loops between 9 a.m. and 3 p.m. through mid-January to install temporary decking, shields and barriers for contractor crews to perform a bridge cleaning and painting project in early 2023.    
   
       
Calvert County           
        
MD 4 at Mount Harmony Road – Median closure and crossover work for intersection reconstruction - Daytime single lane closure along northbound and southbound MD 4 between 9 a.m. and 3 p.m. if needed.      
        
        
Carroll County                   
    
Springfield Ave (MD 851) between Spout Hill Road and Walnut Ave - Drainage improvement project – Single-lane closure during the work hours of 9 a.m. to 3 p.m. Monday through Friday so crews can safely install a new sewer manhole and pipes underneath Springfield Avenue. MDOT SHA expects the work to be complete this spring.   
          
Dorchester County                                           
US 50 East and West from Old Ocean Gateway to MD 331 (Rhodesdale-Vienna Rd) - Structure replacement –Single lane and shoulder closures 6 a.m. - 6 p.m. through January. Updated      
            
Frederick County        
               
 I-70 at MD 75 (Green Valley Road) – Bridge deck demolition – Single lane closure on I-70 overnight during the following hours:       
•        Daytime Monday through Friday from 9 a.m. to 4 p.m.        
•        Overnight Sunday through Thursday from 10 p.m. to 5 a.m.        
  
       
Harford County                 
       
MD 24 (Vietnam Veterans Memorial Highway) from MD 924 (Tollgate Road/Emmorton Road) to MacPhail Road and from Wheel Road to Singer Road – Pavement Milling and Resurfacing – Overnight temporary single lane closures/traffic lane shifts on MD 24 northbound and southbound between 8 p.m. and 5 a.m. the next morning, Sundays through Thursdays.    
  
  
MD 24 (Vietnam Veterans Memorial Highway) from Singer Road to MacPhail Rd. - Pavement resurfacing - Temporary single lane closures and lane shifts between 8 p.m. and 5 a.m. the next morning, Sunday – Thursday, and on Fridays if needed      
  
  
Montgomery & Prince George’s Counties                                                                    
Purple Line – For a list of active construction and lane closures along the Purple Line alignment, please click HERE​ (MTA project).                             
         
St. Mary’s County                                        
        
MD 5 (Point Lookout Road) between Abell/Moakley Streets and MD 245 (Hollywood Road) - Intersection improvement project -- Single and/or double lane closures, Sunday through Thursday nights, 8 p.m. to 5 a.m.    
                                                  
Worcester County         
MD 378 (Baltimore Ave) from South 1st Street to N. Division  – Milling, patching, paving and striping operations – Double lane closures weekdays 8 a.m. - 4:30 p.m. through January 2023. 
                   

Long-Term Closures                                                               

     
Anne Arundel County                                 
MD 175 (Annapolis Road) between McCarron Court and National Business Parkway – Interchange Reconstruction project at MD 295 (Baltimore Washington Parkway) - Daytime single lane closures along MD 175 between 9 a.m. and 3 p.m.; overnight closure 10 p.m. to 5 a.m. Monday through Thursday of the northbound MD 295 to eastbound MD 175 ramp with a signed detour through early February. Updated 
  
MD 100 between MD 10 and MD 177 (Mountain Road) - Pavement Patching - Daytime single lane closures, 8 p.m. to 5 a.m.   
        
MD 2 between the South River bridge and MD 214 - Pavement Resurfacing and sidewalk reconstruction between 8 p.m. and 5 a.m., Sunday through Thursday nights with lane closures.         
                          
Baltimore County                    
        
I-95 Northbound Express Toll Lanes project by MDTA - Raphel Road bridge over I-95 (JFK Memorial Expressway) - MDTA closed the Raphel Road bridge through early 2023 and traffic is being detoured to the Bradshaw Road overpass.                    
             
I-70 Westbound and Eastbound between the Baltimore City Line and I-695 – Concrete Pavement Resurfacing – Single and double lane closures on I-70 east of I-695 weekdays Monday – Friday 9 a.m. to 3 p.m. and continuous lane and/or ramp closures on selected weekends for concrete pour and cure from 9 p.m. Friday through 5 a.m. Sundays, until early 2023.            
      
I-695 Bridge over US 40 (Baltimore National Pike) - Bridge support structure rehabilitation – Crews are working on repairs to bridge piers and abutments under I-695 with long-term traffic shifts and temporary lane closures on US 40 eastbound and westbound underneath I-695 in Catonsville through early spring 2023.  
  
I-695 North (Beltway Inner Loop) Noise Wall from MD 144 to US 40 – Construction of new noise wall – Single lane, ramp and shoulder closures possible along I-695 Inner Loop from MD 144 to Edmondson Ave. during off-peak hours when necessary for installation of noise wall.  Interchange ramp closures possible Sunday – Thursday between 8 p.m. and 5 a.m. the next day (will be posted on message boards in advance)  
   
US 40 (Pulaski Highway) Dual Bridges over Little Gunpowder Falls and (Big) Gunpowder Falls - Bridge Rehabilitation – Construction work will proceed on all four bridges through spring 2023, with ongoing temporary single lane closures on eastbound and westbound US 40 in the vicinity of the bridges during the following off-peak times:  Daytime (Monday – Saturday) Westbound US 40: 8 a.m. to 4 p.m.  Eastbound US 40: 7 a.m.  to 4 p.m.  Overnight (Sunday – Thursday) Westbound and Eastbound US 40:  7 p.m. to 5 a.m. the next day.  Note: The weekend and weekday work with 24/7 lane closures to replace the concrete stop pad section of the right lane of the westbound US 40 approach to Joppa Farm Road scheduled for Dec. 2-9 has been postponed due to weather and now will be rescheduled to early 2023.  Note: Traffic Impacts in Harford County.        
     
MD 25 (Falls Road) between Baltimore City / County Line and I-695 – Baltimore County DPWT water line replacement project - Overnight lane closures with flagging operations along sections of Falls Road, 9 p.m. - 5 a.m. the next day Sunday – Thursday, with some daytime work as needed 9 a.m. - 3 p.m. through spring 2024.           
                            
MD 26 (Liberty Road) between Brenbrook Drive and N. Rolling Road - ADA Sidewalk Reconstruction/Upgrades - Occasional temporary overnight single lane closures on MD 26 between 9 p.m. and 5 a.m. the next day Sunday - Thursday and now between 9 a.m. and 12:30 p.m. Monday – Thursday through early 2023.                             
                                
MD 26 (Liberty Rd.) from I-695 to North Rolling Rd. – ADA Sidewalk Improvements - Overnight single lane closures along this section of Liberty Road Sundays through Thursdays between 9 p.m. and 5 a.m. the following morning.  Daytime single lane closures on this section of Liberty Road possible Mondays through Fridays between 9 a.m. and 12:30 p.m.           
  
MD 30 (Hanover Pike) at Rue St. Lo Drive – Slope stabilization, curb and gutter and roadway resurfacing - Lane closures on MD 30 with flagging operations 9 a.m. - 3 p.m. Monday through Friday beginning winter 2023 through early summer 2023. Updated         
  
MD 30 (Hanover Pike) at Mt. Gilead Rd. – Intersection safety improvements – Periodic lane closures on MD 30 with flagging operations to install reflective pavement markers, center line rumble strips and striping, 9 a.m. - 3 p.m. Monday through Friday through early spring 2023. Updated      
                                                       
MD 43 (White Marsh Blvd.) at Honeygo Blvd. - Intersection Widening and Improvements - Temporary daytime lane closures on MD 43 and Honeygo Blvd. legs of the intersection between 9 a.m. and 3 p.m. Monday-Friday, and overnight lane closures at any time between 8 p.m. and 5 a.m. the next day Sunday-Thursday. When necessary, there will be temporary lane closures on weekends, 7 a.m. - 1 p.m. Saturday and/or Sunday through spring 2023. Updated       
                                                               
MD 140 (Reisterstown Road) between I-695 and Mt. Wilson Lane/ Grey Rock Rd. with MD 140 at Hooks Lane - Americans with Disabilities Act (ADA) improvements - includes traffic signal upgrades, crosswalk markings, and paving on MD 140 and also on Hooks Lane at MD 140. Temporary daytime single lane closures on MD 140 between 9 a.m. and 3 p.m. Monday – Friday and overnight single lane closures on Hooks Lane approach to MD 140 between 9 p.m. and 5 a.m. the next morning Sunday – Thursday. Work continues through spring 2023.                                
MD 140 (Reisterstown Rd.) between E. Pleasant Hill Rd. and Stocksdale Ave. –Resurfacing/County Water Main replacement - Daytime single lane closures Monday - Friday 9 a.m. - 3 p.m. between E. Pleasant Hill Rd and Stocksdale Ave.  Nighttime single lane closures within project limits Sunday – Thursday nights between 8 p.m. and 6 a.m. the next day. Access to driveways in this section will be maintained during any lane closures.  Project scheduled through late summer 2024.                       
                                        
MD 147 (Harford Road) / Joppa Road - Intersection Improvements - Occasional daytime single lane closures and flagging operations on Harford and Joppa Roads in the vicinity of the intersection Monday – Thursday 9 a.m. - 4 p.m. Monday – Thursday and 9 a.m. - 3 p.m.  Fridays. Occasional overnight work with lane closures Sunday – Thursday 9 p.m. - 5 a.m. the next day through winter 2023. Updated  
  
MD 151 (Sparrows Point Blvd.) / Wharf Road (MD 151 B) Interchange - Three-bridge replacement project at interchange – New traffic pattern in effect: Northbound and southbound Wharf Road (and the northern bridge) are now open to traffic between MD 158 (Bethlehem Blvd.) and the left-turn ramp to MD 151. This ramp / bridge is now open for direct access TPA. Wharf Road remains closed underneath both the MD 151 bridge (southern bridge) and the ramp bridge (middle bridge) for bridge construction through spring 2024. Bridge replacement and other construction work within the interchange scheduled to continue through summer 2024.         
   
Calvert County  
MD 2/4 (Solomons Island Road) - Guardrail Installation (varied locations) - Motorists can expect shoulder and occasional off-peak single-lane closures (if needed) between 9 a.m. and 3 p.m. weekdays.   
  
Charles County                      
Eastbound MD 228 at Western Parkway – Intersection Improvements - 9 p.m. to 5 a.m., Sunday nights through Friday mornings, and 9 a.m. to 3 p.m. weekdays.    
                                 
Cecil County                                                                                               
 
MD 213 (Augustine Herman Highway) bridge over C&D Canal in Chesapeake City – U.S. Army Corps of Engineers bridge repair project. Occasional single lane closures and flagging will occur 8 a.m. to 2 p.m., Monday-Thursday.                                                                          
                          
Frederick County                                                      
         
Northbound US 15 Bridge over MD 77 – Bridge Deck replacement project – The right lane is closed. Each side of the bridge is expected to take six to eight months to finish. The entire project is expected to be complete by spring 2023.                                               
                                
Harford County                                                                                  
I-95 Northbound Express Toll Lanes project by MDTA – Replacement of Abingdon Road Bridge over I-95. MDTA has closed the bridge and locally detoured it until spring 2023.       
                                                                               
 I-95 Northbound Express Toll Lanes project by MDTA - I-95/MD 152 Interchange Reconstruction and Park and Ride Lot Relocation - Old Park and Ride lot closed late 2021, new Park and Ride Lot scheduled for completion late 2025.  Construction of the NB I-95 roadway began spring 2021 and is anticipated to be complete fall 2024.    
   
Howard County             
         
MD 94 bridge over I-70 - Bridge deck replacement project - Northbound MD 94 lane is closed.                          
                          
Montgomery County                                                              
        
MD 97 (Georgia Avenue) from north of Gold Mine Road to south of Holiday Drive - MD 97 relocation project. Intermittent off-peak single and multiple lane closures, weekdays, 8 a.m. to 4 p.m. and overnight, Sunday through Thursday, 9 p.m. to 5 a.m.               
      
Brookeville Road from MD 97 (Georgia Avenue) to Grayheaven Manor Road. Sewer relocation project. Full 24/7 road closure with detour through late fall 2022. Drivers should add extra commute time and use MD 97 and MD 108 as alternate routes.              
      
Brighton Dam Road near MD 97 (Georgia Avenue). MD 97 relocation project excavation and new road resurfacing work. Off-road activity with an intermittent off-peak flagging operation and single lane closures, Sunday through Saturday from sunrise to sunset.  
     
MD 108 (Olney Sandy Spring Road) from Olney Mill Road to Brooke Road. Safety and   resurfacing project. Off-peak single daytime lane closures, weekdays, 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 8 p.m. to 5 a.m.  through late summer 2023.           
       
MD 185 (Connecticut Avenue) at Jones Bridge Road/Kensington Parkway Intersection improvement project - Single off-peak lane closures on MD 185, weekdays, 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 9 p.m. to 5 a.m. and single off-peak lane closures on Jones Bridge Road, weekdays, 9 a.m. to 3 p.m. and overnight, 7 days per week, 9 p.m. to 5 a.m. through late summer 2023.         
      
MD 187 (Old Georgetown Road) from Tilden Lane to Nicholson Lane/ Safety and resurfacing project. Off-peak single daytime weekday lane closures, 9 a.m. to 3 p.m. and overnight lane closures, Sunday through Thursday, 8 p.m. to 5 a.m.       
                     
Southbound I-270 between I-70 and I-495 (Capital Beltway) - Traffic congestion relief construction project - Intermittent single lane closures, weekdays, 10 a.m. to 3 p.m. and single, double, and triple overnight lane closures, Sunday through Thursday, 7 p.m. to 5 a.m. and intermittent temporary ramp closures with detours up to 24 hours a day through late summer 2023.                                                                          
              
Prince George’s County         
       
US 1 (Baltimore Avenue) College Avenue to MD 193 (University Boulevard) - US 1 Reconstruction Project - Corridor Improvement- Northbound and southbound single lane closures throughout the length of the project Saturday through Sunday, 10 a.m. to 4 p.m. and 9 p.m. tm. through late summer 2023.                    
               
US 1 (Baltimore Avenue) from Rhode Island Avenue to MD 212A (Powder Mill Road). Safety and resurfacing project. Off peak single and multiple lane closures, weekdays, 9 a.m. to 3 p.m. through late summer 2023.                
                
US 1 (Rhode Island Avenue) from Charles Armentrout Drive to Farragut Street. Rhode Island Avenue Trolley Trail project. Single and multiple off-peak lane closures, weekdays, 9 a.m. to 3 p.m. through year-end 2023.         
              
MD 210 at Livingston Road/Kerby Hill Road. Interchange construction project. Intermittent   off-peak single and multiple lane closures, Monday through Saturday, 9 a.m.to 3 p.m. and overnight, Sunday through Thursday, 8 p.m.to 5 a.m.                                                                            
                       
MD 212A (Powder Mill Road) from Pine Street to US 1 (Baltimore Avenue) - Roadway reconstruction project. Intermittent single and multiple lane closures weekdays, 8 a.m. to 4 p.m.                             
                           
MD 223 (Woodyard Road) from Sherwood Drive to Victoria Drive - Sidewalk construction project - Off-peak lane closures, weekdays, 8:30 a.m. to 3:30 p.m. and Saturdays, 8 a.m. to 5 p.m.                            
                                     
MD 223 (Woodyard Road) at Dower House Road - Geometric improvement project - Single weekday lane closures, 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 9 p.m. to 5 a.m. through late fall 2022.        
                          
MD  500 (Queens Chapel Road) from Eastern Avenue to MD 208 (Hamilton Street) Community safety and enhancement project. Intermittent single and multiple lane closures weekdays,9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 7 p.m. to 6 a.m.      
                              
US 1 (Baltimore Avenue) over I-495 (Capital Beltway) - Bridge painting and cleaning project. Single and multiple off-peak lane closures; 8 p.m. to 5 a.m. through year-end 2022.    
   
Queen Anne’s County         
       
US 301 (Blue Star Memorial Highway) between MD 291 and Pfalzgroff  Lane – Bridge replacement. US 301 is reduced to one lane in each direction through Fall 2023. Northbound traffic is being shifted across the median to run on one lane of the southbound alignment. This is an ASE (Automated Speed Enforcement) work zone with a reduced speed limit of 45 mph.    
       
Talbot County                                                              
       
MD 33 (Talbot St.) from Spencer Ave. to Lee St. in St. Michaels - Sidewalk project. Occasional single-lane closures and flagging 9 a.m. to 3 p.m. Monday-Thursday through spring 2023.                 
                                                                
Washington County                     
        
Eastbound and westbound I-70 at the MD 65 (Sharpsburg Pike) – Bridge rehabilitation and widening of I-70 bridges over MD 65 –   Motorists should expect periodic shoulder work and nighttime lane closures.           





###