PLANNED MAJOR LANE CLOSURE UPDATE FOR WEEKEND OF MAY 6, 2022

MDOT SHA Logo

MDOT SHA Logo

 All Work is Weather Dependent

Real-Time travel conditions and live traffic cameras md511.maryland.gov 

Weekend     

Baltimore County/Harford County line

  • US 40 Dual Bridges over Little Gunpowder Falls and (Big) Gunpowder Falls -Bridge rehabilitation – Single-lane closures possible on US 40 in the vicinity of the bridges on Saturdays through spring 2022.  Eastbound US 40: 7 a.m.  to 4 p.m. Westbound US 40: 8 a.m. to 4 p.m.

Frederick County

  • US 340 bridge over Catoctin Creek past MD 180 (Jefferson Pike) exit - Bridge surface and deck repairs – Eastbound US 340 is finished. Crews are now working 24/7 work on the left lane of westbound US 340. The project is expected to be completed this month. Motorists are advised to take an alternate route during the project to avoid travel delays.  

Wicomico County

  • US 50 East and West from US 13 (Salisbury Bypass) to Walston Switch Rd – Milling, patching, paving and marking operations.  Double lane, shoulder and ramp closures Monday through Saturday 7 a.m.-7 p.m. through June 3. Updated

Week Ahead 

Baltimore County

  • I-695 Outer Loop from I-83 northbound to Stevenson Road – ITS Underground Installation and Roadway construction – Right Shoulder Closures from Monday, May 9 to Friday May 13, 9 a.m. to 3 p.m. New
  • I-695  Inner/Outer Loop from US 40 to I-95 – Test Pits and Pipe Investigation – Intermittent Right/Left Shoulder Closures from Monday, May 9 to Friday, May 13, 9 a.m. to 3 p.m. New
  • I-695 Outer Loop from Stevenson Road to Reisterstown Road – Right/Left Double Lane Closures from Wednesday, May 11 to Thursday, May 12, 10 p.m. to 5 a.m. New
  • I-695 Interchange Ramps at US 1 and at MD 147 – Guardrail Replacement on Ramps - I-695 East (Inner Loop) ramp to US 1 (Belair Road) South: 9 p.m. Sunday, May 8, to 5 a.m. Monday, May 9, and 9 p.m. Monday, May 9, to 5 a.m. Tuesday, May 10.  US 1 South ramp to I-695 West (Outer Loop): 9 p.m. Tuesday, May 10 to 5 a.m. Wednesday, May 11, and 9 p.m. Wednesday, May 11 to 5 a.m. Thursday, May 12.  MD 147 North (Harford Rd.) ramp to I-695 West (Outer Loop): 9 p.m. Thursday, May 12, to 5 a.m. Friday, May 13, and 9 p.m. Sunday, May 15, to 5 a.m. Monday, May 16. New
  • I-70 Westbound between MD 122 (Security Boulevard) and I-695 (Baltimore Beltway) - Repair and resurfacing work - Continuous weekend lane closures will begin on Friday, May 6, Friday 7 p.m. to 5 a.m. Monday, and subsequent weekends until expected completion in late June.
  • Raphael Road overpass at I-95 – MDTA Reconstruction – MDTA closed the Raphael Road overpass as part of the I-95 Express Toll Lanes (ETL) Northbound Extension project. The closure will be in place through early 2023 and traffic is being detoured to the Bradshaw Road overpass.
  • US 40 (Pulaski Highway) from MD 43 (White Marsh Blvd.) to Reames Road - Roadway milling, patching and resurfacing – Weekday single lane closures between 9 a.m. and 3 p.m. Monday-Friday through early May.
  • US 40 (Pulaski Highway) from Campbell Boulevard to MD 700 (Martin Boulevard) – Roadway milling and resurfacing - Weekday single lane closures between 9 a.m. and 3 p.m. through late May.
  • MD 7 (Philadelphia Road) from Ebenezer Road to New Forge Road - Roadway milling and patching – Weekday single lane closures with flagging operations, 9 a.m. to 3 p.m., through late June.
  • MD 30 (Hanover Pike) at Mt. Gilead Road – Intersection Improvements – Daytime lane closures with flagging operations at intersection Monday through Friday, 9 a.m. – 3 p.m. through fall 2022.
  • MD 45 (York Road) Northbound near Boxwood Lane and southbound York Road near Sherwood Road / BGE Electric Reliability Project Spring 2022 - BGE will shift travel lanes to create two work zones around BGE manholes in roadway.  BGE will maintain two-way through traffic through the two work zones, BGE work will be 24/7 through late June 2022.
  • MD 122 (Security Blvd.) from Rolling Rd. to east of I-695 - Roadway milling, patching and resurfacing – Occasional weeknight single lane closures between 9 p.m. and 5 a.m. the next day, Sunday-Thursday as weather permits through mid-May.
  • MD 140 Northbound at Olive Lane / BGE Electric Reliability Project Spring 2022 - Through mid-May 2022, BGE will maintain two through lanes and the left turn lane along northbound MD 140.  Right turns in and out of properties on Olive Lane will be maintained throughout construction. Left turns in and out of Olive Lane and the businesses directly south of Olive Lane will be restricted. BGE will maintain all through lanes along southbound MD 140 through the work zone.
  • MD 145 (Sweet Air Road) from east of MD 146 (Jarrettsville Pike) to Manor Rd.  - Highway maintenance pavement patching, milling, and resurfacing with temporary lane closures and flagging operations on weekdays 9 a.m.-3 p.m. and Saturdays 6 a.m. - 2 p.m. through late June.
  • MD 151 (North Point Blvd.) from New Battle Grove Road to Cove Road – Highway maintenance pavement patching, milling, and resurfacing with temporary lane closures on weekdays between 9 a.m. and 3 p.m. through late June.
  • US 1 (Belair Road) from Chapel Road to Honeygo Boulevard – Highway maintenance pavement patching with temporary lane closures on weekdays between 9 a.m. and 3 p.m. through mid-May.
  • US 1 (Belair Road) from Open Bible Way to north of the Little Gunpowder Falls (Baltimore/Harford County line) - Highway resurfacing project with temporary lane closures on weekdays between 9 a.m. and 3 p.m. through mid-May. 
  • Ingleside Avenue underneath I-695 – ADA Sidewalk Upgrades – Temporary single-lane closures and flagging operations on Ingleside Avenue in the vicinity of the I-695 bridge on weekdays 9 a.m. to 3 p.m. until early summer. New

Carroll County

  • MD 97 (New Washington Road) between MD 140 (Baltimore Boulevard) and the Fenby Park & Ride, south of MD 32 (Sykesville Road) - Highway patching and resurfacing project – Single lane closure and flagging operation overnight from 8 p.m. to 5 a.m. Sunday night through Friday morning. The project is expected to be complete in June.
  • MD 27 (Ridge Road) between Waterville Road and Gillis Falls Road – Highway patching project – Flagging operation overnight Sunday night through Friday morning from 7 p.m. to 6 a.m. The project is expected to be complete in June.

Charles County

  • MD 6 near Maryland Point Road – Temporary roadway closure for pipe replacement on Saturday, May 14 at 8 a.m.; traffic will be guided using a local detour. . NEW

Dorchester County

  • US 50 East and West between Woods Rd and MD 16 (Church Creek Rd) - Utility Work.  Lane and shoulder closures weekdays 7 a.m. - 5 p.m. through July 29. Updated

Frederick County

  • US 15 between Basford Road and the bridge over the Potomac River near the Maryland/Virginia line - Highway patching and resurfacing project - Single Lane closure during overnight mobile project. Crews working Sunday night through Friday morning from 7 p.m. to 5 a.m. The project includes the traffic circle at MD 464 (Point of Rocks Road). Completion is expected in May.
  • MD 26 (Liberty Road) between Chestnut Grove Road and MD 75 (Green Valley Road) - Highway patching project – Weekdays from 8 a.m. to 4 p.m. The project is expected to be complete in May.
  • MD 144 (Main Street) between I-70 and Ijamsville Road – Pipe installation – MDOT SHA closed a 1,000-foot section of westbound MD 144. Emergency vehicles will have access during the temporary closure. The closure is expected to be in effect through May.
  • MD 180 (Jefferson Pike) between Lander Road/Holter Road and the Mount Zion Road traffic circle – Highway patching and resurfacing project – Single lane closure and flagging operation Monday through Friday from 9 a.m. to 3 p.m. This project is expected to be complete in June. 

Harford County

  • US 1 Hickory Bypass from US 1 Business to the northern “T” intersection with US 1 (Conowingo Road). - Highway pavement repair and resurfacing project – Weekday single lane closures between 9 a.m. and 3 p.m. Monday-Friday through late spring 2022.
  • US 1 Business from the signalized intersection with US 1 Hickory Bypass and the northern “T” intersection with US 1 (Conowingo Road) – Highway maintenance pavement patching – Weekdays single lane closures 9 a.m. and 3 p.m. through late spring 2022.
  • MD 23 (East-West Highway) from Commerce Road to US 1 Hickory Bypass – Highway maintenance pavement patching – Weekday single lane closures and flagging operations between 9 a.m. and 4 p.m. through late spring 2022.
  • MD 23 from MD 439 (Old York Road) to the Old York Road just south of MD 138 (Troyer Road) and north of the Jarrettsville Volunteer Fire Company – Highway maintenance pavement patching with temporary lane closures and flagging operations on weekdays between 9 a.m. and 3 p.m. through late June.
  • MD 7 from MD 152 to Fashion Way - Highway Maintenance pavement patching work - Weekday single lane closures with flagging operations, as weather permits, between 9 a.m. and 3 p.m. Monday-Friday through mid-May 2022.
  • MD 136 from Telegraph Road to MD 165 - Highway Maintenance pavement patching work - Weekday single lane closures with flagging operations, as weather permits, between 8 a.m. and 4 p.m. Monday-Friday through mid-May 2022.
  • MD 146 (Jarrettsville Road) from Pocock Road to MD 23 (Norrisville Road) - Highway maintenance pavement patching with temporary lane closures and flagging operations on weekdays between 9 a.m. and 3 p.m. through late June 2022.
  • MD 165 from MD 24 (Rocks Road) to North Harford High School driveway - Highway maintenance pavement patching – Overnight single lane closures and flagging operations on this section of MD 165 overnight, Sunday-Thursday between 9 p.m. and 5 a.m. the next day as weather permits through mid-May 2022.
  • MD 646 (Prospect Road) from MD 543 (Ady Road) to MD 136 (Whiteford Road) – Highway maintenance pavement patching – Temporary daytime lane closures with flagging operations Monday through Friday between 9 a.m. and 3 p.m. through late June.

Howard County

  • Westbound I-70 between westbound US 40 (Baltimore National Pike) merge ramp and MD 97 (Hoods Mill Road) - Highway patching and resurfacing project – Single lane closure and exit ramp detours at MD 32 and MD 97 when crews are working in that area. The schedule is overnight from Sunday evening to Friday morning from 8 p.m. to 5 a.m. This project is expected to be complete by July.
  • Southbound MD 32 (Patuxent Freeway) between the I-70 ramps and Nixon Farm Lane – Construction Traffic Shift – Starting Monday, May 9 at 9 a.m., crews will move traffic from the existing southbound travel lane to the newly constructed lane. The traffic shift will continue uninterrupted all day and overnight before concluding by 5 a.m. on Tuesday, May 10. 
  • MD 32 (Patuxent Freeway) between US 1 (Washington Boulevard) and the Howard/Anne Arundel Co line (south of Dorsey Run Road) – Guardrail upgrades – Single lane and shoulder closures starting Monday, May 9 as crews replace guardrail. The work schedule is Sunday night through Friday morning from 9 p.m. to 5 a.m. This project is expected to be complete in June. 
  • MD 108 (Clarksville Pike) between MD 32 (Patuxent Freeway) and the Howard/Montgomery Co line, past Wainwright Road – Highway patching and resurfacing project – Single lane closure and flagging operation Sunday night through Friday morning from 8 p.m. to 5 a.m. The project is expected to be complete in June. 

Montgomery & Prince George’s Counties

  • Purple Line – For a list of active construction and lane closures along the Purple Line alignment, please click HERE (MTA project).
  • Brookeville Road from MD 97 (Georgia Avenue) to Grayheaven Manor Road. Sewer relocation project begins Wednesday, May 11. Full 24/7 road closure with detour through late spring 2022. Drivers should add extra commute time and use MD 97 and MD 108 (Olney Laytonsville Road) as alternate routes. New
  • Cherry Hill Road over I-95 northbound ramp at the Outer Loop of I-495 (Capital Beltway). Bridge painting and cleaning project begins Monday, May 9. Single and multiple off-peak lane closures, 8 p.m. to 5 .am. through late fall 2022.  New

Somerset County

  • US 13 North between MD 364 (Dividing Creek Rd) and Worcester County Line.  Nighttime marking operations.  Double lane and shoulder closures Sunday – Thursday 7:00 p.m.-6:00 a.m. through May 27. New
  • US 13 North and South between Jones Rd and Wicomico County Line - Nighttime marking operations.  Double lane and shoulder closures Sunday-Thursday 7:00 p.m.-6:00 a.m. through May 27. New
  • US 13 North and South between MD 362 (Mt Vernon Rd) and MD 822 (UMES Blvd) - Utility Work.  Double lane and shoulder closures weekdays 9:00 a.m.-3:00 p.m. through May 20. New
  • US 13 North between MD 673a (Sam Barnes Rd) and MD 413 (Crisfield Highway) Utility Work.  Double lane and shoulder closures weekdays 9:00a.m. - 3:00p.m. through May 20. New
  • US 13 South at MD 822 (UMES Blvd) Construction.  Double lane and shoulder closures weekdays 7 a.m. to 5 p.m. through May 31. New
  • US 13 North and South between Old Eden Rd and Dividing Creek Rd - Utility Work. Double lane and shoulder closures with flagging operations weekdays 9 a.m.-3 p.m. through May.

St. Mary’s County

  • MD 5 between Abell/Moakley Streets and MD 245 (Hollywood Road) - Single and/or double lane closures, Sunday through Thursday nights, 8 p.m. to 5 a.m. for storm drain installation.
  • MD 5 between Camp Brown Road and Scotland Beach Road – Weekday daytime single lane closures between 8 a.m. and 4 p.m.
  • MD 4 between the Thomas Johnson Bridge and MD 235 - Pavement resurfacing -Overnight flagging operation between 9 p.m. and 5 a.m. Sundays through Thursdays within two different sections through spring.

Washington County

  • US 40 Alt (Old National Pike) and MD 34 Boonsboro - Flagging operation - Patching, grind, pave and replace pavement markings - Crews will work daily, 7 a.m. to 3 p.m. Weather permitting, the project is expected to be complete in early May.

Wicomico County

  • US 50 West between Walston Switch and Hobbs Rd. - Guardrail repair.  Double lane and shoulder closures weekdays 9:00 a.m.-3:00 p.m. through May 26 New
  • US 50 East between Bent Pine Rd and MD 346 (Old Ocean City Blvd) Worcester County – Nighttime line striping. Double lane and shoulder closures Sunday-Friday 8 p.m.-7 a.m. through May 27. New
  • US 50, east of Naylor Mill Rd. - Utility Work.  Double lane and shoulder closures weekdays 9 a.m. - 3 p.m. through May 19.
  • US 50 East and West between Cypress St and N. Division St – Night time bridge maintenance. Three lane and shoulder closures weeknights 8 p.m.-6 a.m. through May 31.
  • US 13 North between Naylor Mill Rd & North Pointe Dr. - Utility Work.  Three lane and shoulder closures weekdays 7 a.m. - 4 p.m. through May 26.
  • US 13 South between Columbia Rd and Arlington Rd – Utility Work.  Double lane and shoulder closures weekdays 8 a.m.-4 p.m. through May 25.
  • US 13 North and South between E. Carroll St and E. Church St – Structure repair.  Double lane and shoulder closures weekdays 7 a.m.-4 p.m. through May 31.
  • US 13 North and South between Cedar Ln and Pine Bluff Rd – Structure repair.  Double lane and shoulder closures weekdays 7 a.m.-4 p.m. through May 31.
  • US 50 East between Queen Ave and Owens Branch Rd. Utility Work.  Double lane and shoulder closures weekdays 8 a.m. - 5 p.m. through May 20.
  • US 50 East and West at Boundary St - Utility Work. Lane and shoulder closures weekdays 9 a.m.-3 p.m. through May.

Worcester County

  • MD 528 North and South between 60th and 146th St. - Nighttime marking operations.  Three lane and shoulder closures Sunday-Thursday 7 p.m.-6 a.m. through May 27. New
  • MD 528 North and South between 40th and 62nd St – Landscape Management. Three lane and shoulder closures weekdays 7 a.m.-4 p.m. through May 26. New
  • MD 528 North and South between 17th and 130th Street – Traffic Signal Work. Three lane and shoulder closure weekdays 7 a.m.-4 p.m. through June 6. 
  • US 50 East and West between MD 528 (Philadelphia Ave) and Golf Course Rd – Nighttime bridge repair.  Double lane and shoulder closures Sunday through Thursday 9:00 p.m.-6:00 a.m. through May 26 New
  • US 113 North between US​ 113B (Market St) and Timmons St – Guardrail repair. Double lane and shoulder closures weekdays 9 a.m.-3 p.m. through May 13. New
  • US 113 North between MD 376 (Bay St) and Branch St. - Utility Work.  Double lane and shoulder closures weekdays 7 a.m.-6 p.m. through May 26. Updated
  • US 113 North between Old Snow Hill Rd & Lambertson Rd. - Tree trimming.  Double lane and shoulder closure weekdays 7 a.m.-4 p.m. through May 26.
  • US 113 North and South between MD 365 (Public Landing Rd) and Brick Kiln Rd. - Utility Work.  Utility Work.  Double lane and shoulder closures weekdays 9 a.m.-3 p.m. through May 20.
  • MD 354 North and South between MD 12 (Snow Hil Rd) and Whiton Crossing Rd. Milling, patching, paving and marking.  Single lane and shoulder closure, with flagging operations, weekdays 7 a.m.-5 p.m. through July 1. New
  • US 113 North between Betheden Church Rd and Woodside Lane Utility Work. Double lane and shoulder closures weekdays 8 a.m.-5 p.m. through May 20.
  • MD 528 North and South from 123rd to 146th Street - Utility work.  Three lanes and shoulder closures weekdays 8:00a.m.-5:00p.m. through May 20.
  • MD 528 North and South from 62nd to 146th Street - Thermoplastic striping.  Three lanes and shoulder closures Monday-Thursday 6:30  a.m.-7 p.m. through May 26.
  • MD 378 North between Dorchester and Somerset St. - Three lane and shoulder closures weekdays 7 a.m.-3 p.m. through May 13.

Long-Term Closures

Allegany County

  • MD 51 (Industrial Blvd.) from Canal Parkway to Springdale Street – Left lane closures will be in place in both north and south bound directions. Crews will work daily, 7 a.m. to 7 p.m., on the section of the roadway between Canal Parkway and Springdale Street.  Weather permitting, the project is expected to be completed by the end of June.
  • MD 51 (Oldtown Road) Bridge over the C&O Canal – Crews will be closing both lanes and creating a single lane in the center of the roadway.  This traffic set up will include a temporary traffic signal alternating traffic through the single lane.  Weather permitting, the project is expected to be completed by the end of summer.
  • MD 36 (New George’s Creek Road) from the Salt Dome to Barton - Flagging operation for a safety and resurfacing project – Patch, grind, and resurface and apply new pavement markings - Crews will work daily, 7 a.m. to 7 p.m.
  • I-68 (National Freeway) Bridge over MD 55 (Vale Summit Road) - Barrier repairs and fencing installation - Weekdays from 7 a.m. to 7 p.m. Right lane and shoulder closures both westbound and eastbound - Weather permitting, the project is expected to complete by the end of June.

Anne Arundel County

  • MD 170 (Belle Grove Road) between Sixth Avenue and 10th Avenue – Temporary overnight detour between 9 p.m. and 5 a.m., Sunday through Thursday for utility work. New
  • MD 424 between MD 214 and US 50 – Daytime single lane closures between 9 a.m. and 3 p.m. for resurfacing. New
  • MD 648 between MD 3 and I-97 – Nighttime single lane closures between 9 p.m. and 5 a.m. for pavement resurfacing, Sunday through Thursday.    
  • MD 424 between Lang Drive and the Crofton High School entrance – Daytime lane shift from 9 a.m. to 2 p.m., Monday through Friday for maintenance work.

Baltimore County

  • Cove Road bridge over I-695 - Bridge deck replacement - On I-695, daytime single lane closures in both directions may occur Monday-Friday between 9 a.m. and 3 p.m. and overnight lane closures Sunday-Thursday between 7 p.m. and 5 a.m. the next day. On the Cove Road bridge over I-695, long-term single lane closures are in effect, with two-way traffic on the southern (eastbound) side of the bridge deck, through late summer 2022.
  • I-83 (Baltimore-Harrisburg Expressway) North and South Bridges over Padonia Road – Dual Bridge replacement and interchange improvements through summer 2022. There may be single lane closures on I-83 north and I-83 south between 9 a.m. and 4 p.m. Monday-Friday and between 7 p.m. and 5 a.m. the next day Sunday-Thursday. Single lane closures on Padonia Rd. West between 9 a.m. and 3 p.m. Monday-Saturday, and between 8 p.m.  and 5 a.m. the next day Sunday-Thursday. Detours of Padonia Rd. underneath I-83 possible on any weeknight (Sunday-Thursday) between 8 p.m. and 5 a.m. the next morning. Interchange Ramp from Padonia Road East to I-83 North closed 24 hours/7 days until entire project is complete summer 2022.
  • US 40 Dual Bridges over Little Gunpowder Falls and (Big) Gunpowder Falls – Four bridges to be replaced between White Marsh and Joppatowne – Motorists should expect temporary single lane closures on eastbound and westbound US 40 during the following off-peak times:  Daytime (Monday-Saturday) Westbound US 40: 8 a.m. to 4 p.m.  Eastbound US 40: 7 a.m.  to 4 p.m.  Overnight (Sunday-Thursday) Westbound and Eastbound US 40:  7 p.m. to 5 a.m. the next day.  Note:  The lanes on the eastbound and westbound US 40 bridges over the (Big) Gunpowder Falls will be split through spring 2022.  Possible Traffic Impact in Harford County.
  • US 1 (Washington Blvd.) Bridge over CSX Transportation rail lines – Bridge replacement –  Clarke Blvd. at US 1 is closed/detoured 24 hours/7 days through summer 2022.  Posted detour route includes Selford Rd., Francis Ave., Oregon and Carville Aves., Tom Day Blvd. and US 1 Alt. (Southwestern Blvd.)   Project scheduled through late fall 2022.
  • MD 25 (Falls Road) between Baltimore City / County Line and I-695 – Baltimore County DPW water line replacement project - Overnight lane closures with flagging operations along sections of Falls Road, 9 p.m.-5 a.m. the next day Sunday-Thursday, with some daytime work as needed 9 a.m.-3 p.m. through spring 2024.
  • MD 26 (Liberty Road) between Brenbrook Drive and N. Rolling Road - ADA Sidewalk Reconstruction/Upgrades - Temporary single lane closures on MD 26 between 9 p.m. and 5 a.m. the next day Sunday-Thursday and between 9 a.m. and 11 a.m. Monday Thursday through spring 2022.
  • MD 26 (Liberty Road) between Deer Park Rd. and  Pikeswood Rd. - Americans with Disabilities Act (ADA) Sidewalk Reconstruction/Upgrades - Temporary single lane closures on MD 26 between 9 a.m. and 3 p.m. Monday-Friday through late spring 2022.
  • MD 30 (Hanover Pike) at Mt. Gilead Road – Intersection Improvements – Daytime lane closures with flagging operations at intersection Monday through Friday, 9 a.m.-3 p.m. through fall 2022.
  • MD 43 (White Marsh Blvd.) at Honeygo Blvd. - Intersection Widening and Improvements - Temporary daytime lane closures on MD 43 and Honeygo Blvd. legs of the intersection between 9 a.m. and 3 p.m. Monday-Friday, and overnight lane closures at any time between 8 p.m. and 5 a.m. the next day Sunday-Thursday. When necessary, there will be temporary lane closures on weekends, 7 a.m.-1 p.m. Saturday and/or Sunday. Project scheduled through late spring 2022.
  • MD 140 (Reisterstown Road) between I-695 and Mt. Wilson Lane/ Grey Rock Rd. - Americans with Disabilities Act (ADA) improvements - includes traffic signal upgrades, crosswalk markings, and paving on MD 140 and also on Hooks Lane at MD 140. Temporary daytime single lane closures on MD 140 between 9 a.m. and 3 p.m. Monday-Friday and overnight single lane closures on Hooks Lane approach to MD 140 between 9 p.m. and 5 a.m. the next morning Sunday-Thursday through summer 2022.
  • MD 140 (Reisterstown Rd.) between Painters Mill Rd. and E. Pleasant Hill Rd. – Resurfacing/County Water Main replacement - Crews are installing new 36-inch water main from Owings Mills Blvd. to East Pleasant Hill Road with connections to fire hydrants and buildings along MD 140. Daytime single lane closures between 9 a.m. and 3 p.m. between Owings Mills Blvd. and E. Pleasant Hill Rd.  Nighttime single lane closures within project limits Sunday-Thursday nights between 9 p.m. and 5 a.m. the next day.  Access to all driveways in this section will be maintained during any lane closures.  Project scheduled through spring 2022.
  • MD 140 (Reisterstown Rd.) between E. Pleasant Hill Rd. and Stocksdale Ave. – Resurfacing/County Water Main replacement - Daytime single lane closures Monday-Friday 9 a.m.-3 p.m. between E. Pleasant Hill Rd and Stocksdale Ave.  Nighttime single lane closures within project limits Sunday-Thursday nights between 8 p.m. and 6 a.m. the next day. Access to driveways in this section will be maintained during any lane closures.  Project scheduled through summer 2024.
  • MD 147 (Harford Road) / Joppa Road - Intersection improvements - Daytime single lane closures and flagging operations on Harford and Joppa Road in the vicinity of the intersection Monday-Thursday 9 a.m.-4 p.m. Monday-Thursday and 9 a.m.-3 p.m.  Fridays. Overnight work with lane closures Sunday-Thursday 9 p.m.-5 a.m. the next day. Traffic shift in effect as of Jan. 26 on westbound Joppa Rd. with lanes shifted to the left approaching Harford Rd.  Traffic shift and right lane closure in effect along southbound MD 147 from Jomat Avenue to south of Joppa Road, through summer 2022.
  • MD 151 (Sparrows Point Blvd.) / Wharf Road (MD 151 B) Interchange - Three-bridge replacement project at interchange.  The southbound side of the existing MD 151 bridge is closed and two-way traffic - one lane in each direction - runs on the northbound side of the bridge. This will be in effect through 2022 and will enable partial demolition of the existing bridge over Wharf Road and future construction of the new bridge.  This is in addition to the detours of southbound and northbound Wharf Road at the interchange for replacement of two other bridges.

Cecil County

  • MD 213 (Augustine Herman Highway) bridge over C&D Canal in Chesapeake City – U.S. Army Corps of Engineers bridge repair project. Occasional single lane closures and flagging will occur 9 a.m. to 3 p.m., Monday-Thursday from May 9 through August 11. View real-time traffic conditions at the bridge with these cameras: MD 213 at Basil Ave. (south side) and MD 213 at Lock St. (north side). New
  • MD 279 (Elkton Road) at MD 277 (Fletchwood Road) – Northbound MD 279 is reduced to a single lane at the MD 277 intersection near the Delaware line and shifted across the median to a contraflow pattern (one lane in each direction).  This is part of the Delaware Department of Transportation (DelDot) reconstruction of route 279.

Frederick County

  • Northbound US 15 Bridge over MD 77 – Bridge deck replacement project – The right lane is closed. Each side of the bridge is expected to take six to eight months to finish. The entire project is expected to be complete by spring 2023.
  • I-270 Southbound from MD 121 (Clarksburg Road) to MD 109 (Old Hundred Road) - I-270 acceleration lane expansion project in Montgomery County. Single and multiple off-peak lane closures, weekdays 9:30 a.m.to 3:30 p.m. and overnight, Sunday through Thursday, 7 p.m. to 4 a.m.  Possible Traffic Impact in Frederick County.

Garrett County

  • MD 39 (Hutton Road) from Ashby Ellis to US 219 in Oakland – Drainage improvement and repaving project, flagging operation, 7 a.m.-5 p.m. Monday-Friday. New
  • US 50 from the West Virginia Line to US 219 – Patching, milling and paving, crews working 7 a.m.-5:00 p.m. through the end of April.

Harford County

  • Old Joppa Road Bridge over I-95 (MDTA project) – Bridge replacement project – Old Joppa Road closed and locally detoured.
  • Clayton Road bridge over I-95 between MD 152 and MD 24 (MDTA project) - Clayton Road closed and detoured until early 2022.
  • I-95/MD 152 Interchange Reconstruction (MDTA project) - Travel lanes on MD 152 at I-95 will be shifted to accommodate reconstruction of the existing interchange. MD 152 traffic will shift from the current location to the outside of the roadway in both directions on MD 152 between Old Mountain Road/Jaycee Drive and MD 7 (Philadelphia Road). All access to and from I-95 will retain its present configuration throughout this phase of construction, which will last through spring 2022.

Montgomery County

  • MD 185 (Connecticut Avenue) at Jones Bridge Road/Kensington Parkway Intersection improvement project. Single off-peak lane closures on MD 185, weekdays, 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 9 p.m. to 5 a.m. and single off-peak lane closures on Jones Bridge Road, weekdays, 9 a.m. to 3 p.m. and overnight, 7 days per week, 9 p.m. to 5 a.m. through late summer 2023.
  • MD 185 (Connecticut Avenue) at Saul Road Intersection improvement project. Single lane closures with intermittent intersection closures, weekdays, 9 a.m. to 3 p.m. through year-end 2022.
  • MD 97 (Georgia Avenue) from north of Gold Mine Road to south of Holiday Drive. - Roadway relocation project - Intermittent single northbound and southbound lane closures weekdays,    9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 9 p.m. to 6 a.m. through year-end 2022.
  • MD 410 (East West Highway) from Rocton Avenue to Curtis Street – Curb realignment and sidewalk construction. Single lane closure, weekdays, 9 a.m. to 3 p.m. through late spring 2022.
  • I-270 from I-70 to I-495 (Capital Beltway) - Traffic congestion relief construction project - Intermittent single lane closures, weekdays, 10 a.m. to 3 p.m. and single, double and triple overnight lane closures, Sunday through Thursday, 7 p.m. to 5 a.m. and intermittent temporary ramp closures with detours up to 24 hours a day through year-end 2022.
  • I-270 Southbound from MD 121 (Clarksburg Road) to MD 109 (Old Hundred Road) - I-270 acceleration lane expansion project. Single and multiple off-peak lane closures, weekdays 9:30 a.m.to 3:30 p.m. and overnight, Sunday through Thursday, 7 p.m. to 4 a.m. through year-end 2022.

Prince George’s County

  • US 1 (Baltimore Avenue), College Ave. to MD 193 (University Boulevard) - US 1 Reconstruction Project - Corridor Improvement- Northbound and southbound single lane closures throughout the length of the project Saturday through Sunday, 10 a.m. to 4 p.m. and 9 p.m. tm. through late summer 2023.
  • MD 5 (Branch Avenue) from the DC Line to the intersection of Curtis Drive - Safety and resurfacing project. Intermittent/temporary single and multiple MD 5 northbound off-peak lane closures, weekdays, 9 a.m. to 3 p.m., overnight, Sunday through Thursday 7 p.m. to 5 a.m. and weekends, 5 a.m. to 10 p.m. and weekends 5 a.m. to 10 p.m. Intermittent/temporary single  and multiple MD 5 southbound off-peak lane closures weekdays, 6 a.m. to 12 noon overnight, Sunday through Thursday, 7 p.m. to 6 a.m. and intermittent/temporary single and multiple    MD 637 single lane closures, weekdays, 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 7 p.m. to 6 a.m. through late summer 2022.
  • MD 5 (Branch Avenue) from Suitland Parkway to Curtis Drive. Median construction. Single northbound lane closure 24 hours a day through late summer 2022.
  • MD 210 (Indian Head Highway) at Kerby Hill Road/Livingston Road. Interchange construction project - Intermittent single and multiple-off peak lane closures on all roads, weekdays, 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 9 p.m. to 5 a.m. and Saturday, 9 a.m. to 3 p.m. through late summer 2022.       
  • MD 212A (Powder Mill Road) from Pine Street to US 1 (Baltimore Avenue) - Roadway reconstruction project. Intermittent single and multiple lane closures weekdays, 8 a.m. to 4 p.m. through late summer 2022.
  • MD 223 (Woodyard Road) from Sherwood Drive to Victoria Drive - Sidewalk construction project - Off-peak lane closures, weekdays, 8:30 a.m. to 3:30 p.m. and Saturdays, 8 a.m. to 5 p.m. through late fall 2022.
  • MD 223 (Woodyard Road) at Dower House Road - Geometric improvement project - Single weekday lane closures, 9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 9 p.m. to 5 a.m. through late summer 2022.
  • MD  500 (Queens Chapel Road) from Eastern Avenue to MD 208 (Hamilton Street) Community safety and enhancement project. Intermittent single and multiple lane closures weekdays,9 a.m. to 3 p.m. and overnight, Sunday through Thursday, 7 p.m. to 6 a.m. through late summer 2022.
  • I-95/I-495 (Capital Beltway) from Suitland Road to MD 4 (Pennsylvania Avenue) - Suitland Parkway bridge replacement project. Road shoulder closure permissible 24 hours daily, intermittent single and multiple lane closures, weekdays, 9 a.m. to 3 p.m. and overnight, Sunday through Friday, 8 p.m. to 6 a.m. through year end 2022.

Talbot County

  • MD 33 (Talbot St.) from Spencer Ave. to Lee St. in St. Michaels - Sidewalk project. Occasional single-lane closures and flagging 9 a.m. to 3 p.m. Monday-Thursday through Spring 2023. New  

Washington County

  •  I-70 East and Westbound at the MD 65 Interchange – Bridge rehabilitation and widening of I-70 bridges over MD 65 - Through September, motorists on I-70 eastbound will follow a posted detour.  I-70 eastbound shifted to the median and the right shoulder is closed with concrete barrier wall.  Updated
  • US 40 East at Beaver Creek Road – Geometric improvements at the intersection, 7 a.m. to 7 p.m. - single lane traffic eastbound, US 40 East in a single lane near Beaver Creek Road and Auto Place. The right turn from US 40 East to Beaver Creek Road will be narrowed during the construction using barrels.
  • MD 632 (Downsville Pike) from MD 68 (Lappans Road) to South of I-70, patching, milling and repaving project, motorists should expect a flagging operation, Monday – Friday 7 a.m. to 3 p.m.  Project to be completed by the beginning of June.

 

###